Drywalling a room is two jobs: hanging the board and finishing the joints. This guide works through both for a 12 × 12 ft room with 8 ft walls, using USG’s installation guide for the quantities and the screw spacing, with a link to the calculator at each step.
The materials list
| Material | For a 12 × 12 room (walls + ceiling, one door) | Worked page |
|---|---|---|
| Drywall | 18 sheets of 4 × 8, or 12 of 4 × 12 (508 sq ft + 10%) | How many sheets of drywall for a 12x12 room |
| Screws | 28 per wall sheet, 35 per ceiling sheet; about 1.4 lb | How many drywall screws per 4x8 sheet |
| Joint compound | about 5 gal: two 4.5 gal pails | How much mud per sheet of drywall |
| Paper tape | about 190 ft: one 250 ft roll | How much drywall tape per sheet |
| Corner bead | one piece per outside corner | Corner bead calculator |
| Primer | about 1.3 gal for walls and ceiling | Primer for new drywall |
Other sizes: how many sheets of drywall for a 10x12 room, and for a garage, how many sheets of drywall for a 2 car garage. For the weight you’ll be carrying, see how much does a bundle of drywall weigh.
Hanging the board
- Ceiling first. Hang ceiling sheets across the joists, tight to each other. A 12 × 12 ceiling takes exactly three 4 × 12 sheets: how many sheets of drywall for a 12x12 ceiling.
- Screws on the ceiling go 12 in apart along every joist (USG’s spacing), 3/8 in or more from the edges: 35 per 4 × 8 sheet on 16 in joists, as on how many drywall screws per sheet for a ceiling.
- Walls next, top sheet first, pushed up against the ceiling sheets so they support the ceiling edges; then the bottom sheet, leaving a small gap at the floor that the baseboard covers.
- Screws on walls go 16 in apart (USG), 28 per 4 × 8 sheet on 16 in studs.
- Stagger butt joints so they don’t line up on the same stud, and keep joints away from the corners of doors and windows, where they crack.
- Cut openings for outlets and switches with a jab saw or rotary tool; measure twice, because patches take more mud than any joint.
Set every screw just below the paper without tearing it. A depth-setting screw gun or a dimpler bit does this consistently; a screw that breaks the paper holds nothing and needs another beside it.
Basements and damp rooms
USG’s wallboard catalog says that where there is a risk of moisture exposure, you should choose panels with adequate resistance to mold growth: its moisture- and mold-resistant boards are labeled Mold Tough, and other makers have their own. Keep the bottom edge just off a concrete slab, because gypsum wicks moisture up (USG’s handling guide stores board on risers for the same reason), and let the baseboard cover the gap. Fix any water coming in before the board goes up; a moisture-resistant panel is not a waterproof one.
Finishing: three coats
- Corner bead on every outside corner, fastened or bedded per its type.
- Tape coat: a band of compound along each joint, paper tape pressed in and the excess squeezed out; creased tape in the inside corners; a first pass over the screws and the bead.
- Fill coat: when dry, a wider coat over the joints, screws and bead with a 10 in knife.
- Finish coat: a thin, feathered coat with a 12 in knife, wider again, followed by light sanding.
Each coat must dry before the next: ready-mixed compound dries overnight in normal conditions, longer in cold or damp rooms. Setting-type compound hardens in a set time printed on the bag, which speeds up the tape coat.
Levels of finish
The Gypsum Association’s levels run from 0 to 5. Level 4 (tape embedded, then further coats over the joints, fasteners and bead, sanded smooth) is the usual for walls getting flat or eggshell paint. Level 5 adds a skim coat over the entire surface, which USG recommends where gloss paints or harsh, raking light would show the difference between paper and mud. A skim coat is a much bigger mud order: see how much joint compound to skim coat a 12x12 room.
Sanding and dust
Sand lightly with a fine sponge or a pole sander, just enough to knock down ridges; over-sanding scuffs the paper. Sanding compound makes fine dust that irritates the airways: USG’s safety data sheet calls for minimizing dust and wearing a NIOSH-approved respirator where exposure isn’t controlled. Close off the room, cover vents, and use a vacuum sander or wet-sand where you can.
Prime, then paint
Prime the whole surface before painting so the paper and the joints absorb paint the same way; otherwise the joints show through as dull or shiny stripes. Then two finish coats: for this room, see how much paint for a 12x12 room.
CalculatorDrywall Calculator (Sheets for a Room) →Sheets, plus USG’s estimate of mud, tape and screws, for your room.Frequently asked questions
Do you hang drywall on the ceiling or walls first?
The ceiling, so the wall sheets can be pushed up under its edges and help support them.
How many coats of mud does drywall need?
Three over flat joints, screws and corner bead is the usual (tape, fill and finish coats) for a Level 4 finish; Level 5 adds a skim coat over everything.
Sources
- USG, How to Install and Finish Sheetrock Brand Gypsum Panels (J371) (opens in a new tab) — Panel coverage table; per 1,000 sq ft of panels: 2.7 lb of Type W screws (12 in on ceilings, 16 in on walls), 5.3 lb of nails, 370 ft of joint tape, about 10 gal of All Purpose or 9 gal of Plus 3 compound; First Coat primer at 400 sq ft/gal.
- USG, Sheetrock Brand All Purpose Joint Compound, Ready-Mixed, submittal sheet (J1969) (opens in a new tab) — Approximately 10 gal per 1,000 sq ft of gypsum panels (37.8 L per 100 m²); 4.5 gal pail, 3.5 and 4.5 gal cartons.
- USG, Finishing and Decorating Gypsum Panels white paper (J2010) (opens in a new tab) — Level 5 finish: skim coat of conventional-weight All Purpose compound, then First Coat primer; “there is no specific mil thickness that constitutes a proper skim coat”.
- USG, Sheetrock Brand All Purpose Joint Compound, Ready-Mixed, safety data sheet (opens in a new tab) — Dust irritates the respiratory system; minimize dust and use a NIOSH-approved respirator where exposure is not controlled.
- USG, Interior Finishing Products catalog (J1424) (opens in a new tab) — Paper joint tape in 75, 250 and 500 ft rolls; corner bead in standard 8, 9 and 10 ft lengths; ceiling spray texture in 32 and 40 lb bags.
- USG, Wallboard catalog (WB2816) (opens in a new tab) — Approximate weights for design and shipping: 1/4 in 1.2, 3/8 in 1.4, 1/2 in UltraLight 1.25, 1/2 in Firecode C 2.0, 5/8 in Firecode X 2.2 lb/sq ft; 48 and 54 in widths. Moisture- and mold-resistant (Mold Tough) panels: “when risk of moisture exposure is present, choose products and systems that offer adequate resistance against mold growth.”
- USG, Storage and handling of gypsum panel products (WB2333) (opens in a new tab) — Keep board dry and off the floor on risers “to prevent moisture from wicking up and wetting the material”; stack flat.